Cost-efficiency - Norway
PRB monitoring
▪ The en route 2023 actual unit cost of Norway was 49.37 €2017, -5.2% lower than the determined unit cost (52.10 €2017). The terminal 2023 actual unit cost was 198.06 €2017, +14% higher than the determined unit cost (173.37 €2017).
▪ The en route 2023 actual service units (2.33M) were slightly higher (+0.5%) than the determined service units (2.32M).
▪ The en route 2023 actual total costs were -5.7 M€2017 (-4.7%) lower than determined. This reduction was largely driven by lower staff costs (-8.7 M€2017, or -11%). According to the NSA, the lower staff costs were due to wage growth that did not meet expectations and an increase in project activity. With more project activity than determined, costs related to these projects, such as the time staff dedicated to developing new assets, were reclassified from staff costs to capital costs.
▪ Avinor ANS spent 27 M€2017 in 2023 related to costs of investments for both en route and terminal charging zones, -11% lower than determined (31 M€2017). This reduction was attributed to the reduction in actual depreciation costs compared to determined figures (-4.9 M€2017, or -35%), owing to the postponement of the new ATM system and a smaller than anticipated impact from leases.
▪ The en route actual unit cost incurred by users in 2023 was 50.16€ (+7.1% above the 2023 DUC), while the terminal actual unit cost incurred by users was 173.41€ (+10% above the 2023 DUC). The difference between the AUCU and the DUC in terminal charging zone is primarily attributed to the inflation mechanism (+3.1 M€).
▪ The en route regulatory result for Avinor amounted to +12 M€, or 11% of the 2023 revenue. This may indicate that the airspace users are charged for costs which have not materialised in 2023. The PRB will take into consideration the implementation of the RP3 performance plan when assessing the RP4 cost-efficiency targets.
En route charging zone
Unit cost (KPI#1)
| Actual and determined data | ||||
| Total costs - nominal (M€) | 2020-2021 | 2022 | 2023 | 2024 |
|---|---|---|---|---|
| Actual costs | 237 | 128 | 136 | NA |
| Determined costs | 236 | 130 | 133 | 136 |
| Difference costs | 1 | -2 | 4 | NA |
| Inflation assumptions | 2020-2021 | 2022 | 2023 | 2024 |
|---|---|---|---|---|
| Determined inflation rate | NA | 2.0% | 2.0% | 2.0% |
| Determined inflation index | NA | 111.2 | 113.4 | 115.6 |
| Actual inflation rate | NA | 6.2% | 5.8% | NA |
| Actual inflation index | NA | 117.7 | 124.5 | NA |
| Difference inflation index (p.p.) | NA | +6.5 | +11.1 | NA |
Actual unit cost incurred by the users (AUCU) (PI#1)
| AUCU components (€/SU) – 2023 | |
| Components of the AUCU in 2023 | €/SU |
|---|---|
| DUC | 46.82 |
| Inflation adjustment | 3.49 |
| Cost exempt from cost-sharing | -0.09 |
| Traffic risk sharing adjustment | 0.00 |
| Traffic adj. (costs not TRS) | -0.02 |
| Finantial incentives | 0.00 |
| Modulation of charges | 0.00 |
| Cross-financing | 0.00 |
| Other revenues | 0.00 |
| Application of lower unit rate | 0.00 |
| Total adjustments | 3.39 |
| AUCU | 50.21 |
| AUCU vs. DUC | + 7.2% |
| Cost exempt from cost sharing by item - 2023 | €'000 | €/SU |
|---|---|---|
| New and existing investments | -2,367.7 | -1.02 |
| Competent authorities and qualified entities costs | 63.3 | 0.03 |
| Eurocontrol costs | 2,104.9 | 0.90 |
| Pension costs | 0.0 | 0.00 |
| Interest on loans | 0.0 | 0.00 |
| Changes in law | 0.0 | 0.00 |
| Total cost exempt from cost risk sharing | -199.5 | -0.09 |