Investments - Estonia
PRB monitoring
▪ EANS planned a total RP3 asset value for new investments of 24M€₂₀₁₇. EANS did not plan any new major investment for RP3.
▪ EANS underspent -1.8M€₂₀₁₇ (-6.4%) in costs related to investments during RP3 (-2.7M€₂₀₁₇ in en route and +1.0M€₂₀₁₇ in terminal), according to the reporting tables. However, in the monitoring reports, EANS reported an underspending of -1.4M€₂₀₁₇ (-5.0%). No explanation for the differences has been provided. These amounts shall be reimbursed to the airspace users through a reduction of future unit rate(s), unless the NSA decides after consultation with the users, that the ANSP shall not reimburse a part of the difference according to article 28 of Regulation (EU) 2019/317.
▪ EANS reported 1.7M€₂₀₁₇ funding from Union assistance programmes in RP3, while SESAR Deployment Manager data indicates payments for 0.3M€₂₀₁₇ during the reference period.
Expected benefit and impact per new major investment Estonia | EANS
| New major investments |
Expected benefit per KPA |
SAF |
ENV |
CAP |
CEF |
| New major investments |
Expected impact |
Network |
Local |
Non-performance |
| New major investments |
SES mandated |
Partnership |
ATM systems
|
| ATM system |
CP/MP |
Public funding granted for total CAPEX (CEF/TEN-T)
Actual funding declaration vs payments
| Funding declared (M€2017) |
2020 |
2021 |
2022 |
2023 |
2024 |
RP3 |
| Total included in the funding declaration (reporting tables) |
0.00 |
0.00 |
0.00 |
0.00 |
1.71 |
1.71 |
| SDM Payment |
0.02 |
0.00 |
0.07 |
0.18 |
0.00 |
0.27 |
| Difference between total funding declared vs received |
(0.02) |
0.00 |
(0.07) |
(0.18) |
1.71 |
1.44 |