Investments - Malta
PRB monitoring
▪ MATS planned a total RP3 asset value for new investments of 8.3M€₂₀₁₇. MATS did not plan any new major investment for RP3.
▪ MATS planned RP3 new investments for represent 0.2% of the Union-wide total amounts of the assets for new investments.
▪ MATS underspent -4.1M€₂₀₁₇ (-25%) in costs related to investments during RP3 (-4.9M€₂₀₁₇ in en route and +0.8M€₂₀₁₇ in terminal), according to the reporting tables. However, in the monitoring reports, MATS reported an underspending of -6.4M€₂₀₁₇ (-30%). No explanation for the differences has been provided. These amounts shall be reimbursed to the airspace users through a reduction of future unit rate(s), unless the NSA decides after consultation with the users, that the ANSP shall not reimburse a part of the difference according to article 28 of Regulation (EU) 2019/317.
▪ MATS reported 0.14M€₂₀₁₇ funding from Union assistance programmes in RP3, which is consistent with SESAR Deployment Manager data.
Expected benefit and impact per new major investment Malta | MATS
| New major investments |
Expected benefit per KPA |
SAF |
ENV |
CAP |
CEF |
| New major investments |
Expected impact |
Network |
Local |
Non-performance |
| New major investments |
SES mandated |
Partnership |
ATM systems
|
| ATM system |
CP/MP |
Public funding granted for total CAPEX (CEF/TEN-T)
Actual funding declaration vs payments
| Funding declared (M€2017) |
2020 |
2021 |
2022 |
2023 |
2024 |
RP3 |
| Total included in the funding declaration (reporting tables) |
-0.61 |
0.01 |
0.57 |
0.17 |
0.00 |
0.14 |
| SDM Payment |
-0.62 |
0.00 |
0.57 |
0.17 |
0.00 |
0.13 |
| Difference between total funding declared vs received |
0.00 |
0.01 |
(0.00) |
0.00 |
0.00 |
0.01 |