Investments - Luxembourg
PRB monitoring
▪ ANA Lux planned a total RP3 asset value for new investments of 14.3M€₂₀₁₇, of which 57% for new major investments. ANA Lux planned six new major investments for RP3, of which two have not started.
▪ ANA Lux planned RP3 new investments represent 0.3% of the Union-wide total amounts of the assets for new investments. ANA Lux planned to invest more in CNS systems compared to the Union-wide median (72% vs 18% respectively).
▪ ANA Lux underspent -2.0M€₂₀₁₇ (-16%) in costs related to investments during RP3 (-0.6M€₂₀₁₇ in en route and -1.4M€₂₀₁₇ in terminal), according to the reporting tables. However, in the monitoring reports, ANA Lux reported an underspending of -1.9M€₂₀₁₇ (-15%). No explanation for the differences has been provided. These amounts shall be reimbursed to the airspace users through a reduction of future unit rate(s), unless the NSA decides after consultation with the users, that the ANSP shall not reimburse a part of the difference according to article 28 of Regulation (EU) 2019/317.
▪ Both ANA Lux and SESAR Deployment Manager reported no funding from Union assistance programmes in RP3.
Expected benefit and impact per new major investment Luxembourg | ANA Lux
| New major investments |
Expected benefit per KPA |
SAF |
ENV |
CAP |
CEF |
| Radar / SUR: A-SMGCS Level 2 and updates |
|
X |
|
X |
|
| Navigation systems: ILS/DME24 |
|
X |
|
|
|
| Communication systems: VCS/VCR, emergency radio; ADD and AMHS |
|
X |
|
|
|
| Aeronautical Systems: AIS/AIM, eTOD and MET |
|
X |
|
|
|
| Radar / SUR: Surveillance chain evolution |
|
|
|
|
|
| Navigation systems: DVOR/DME DIK, DVOR/DME LUX |
|
X |
|
|
|
| New major investments |
Expected impact |
Network |
Local |
Non-performance |
| Radar / SUR: A-SMGCS Level 2 and updates |
|
|
|
|
| Navigation systems: ILS/DME24 |
|
|
|
|
| Communication systems: VCS/VCR, emergency radio; ADD and AMHS |
|
|
|
|
| Aeronautical Systems: AIS/AIM, eTOD and MET |
|
|
|
|
| Radar / SUR: Surveillance chain evolution |
|
|
|
|
| Navigation systems: DVOR/DME DIK, DVOR/DME LUX |
|
|
|
|
| New major investments |
SES mandated |
Partnership |
ATM systems
|
| ATM system |
CP/MP |
| Radar / SUR: A-SMGCS Level 2 and updates |
|
|
X |
X |
| Navigation systems: ILS/DME24 |
|
|
X |
X |
| Communication systems: VCS/VCR, emergency radio; ADD and AMHS |
|
|
X |
X |
| Aeronautical Systems: AIS/AIM, eTOD and MET |
|
|
X |
X |
| Radar / SUR: Surveillance chain evolution |
|
|
X |
|
| Navigation systems: DVOR/DME DIK, DVOR/DME LUX |
|
|
X |
|
Public funding granted for total CAPEX (CEF/TEN-T)
Actual funding declaration vs payments
| Funding declared (M€2017) |
2020 |
2021 |
2022 |
2023 |
2024 |
RP3 |
| Total included in the funding declaration (reporting tables) |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
| SDM Payment |
NA |
NA |
NA |
NA |
NA |
0.00 |
| Difference between total funding declared vs received |
NA |
NA |
NA |
NA |
NA |
0.00 |