• Home
  • SES view
  • State view
    • Austria
    • Belgium
    • Bulgaria
    • Croatia
    • Cyprus
    • Czech Republic
    • Denmark
    • Estonia
    • Finland
    • France
    • Germany
    • Greece
    • Hungary
    • Ireland
    • Italy
    • Latvia
    • Lithuania
    • Luxembourg
    • Malta
    • MUAC
    • Netherlands
    • Norway
    • Poland
    • Portugal
    • Romania
    • Slovakia
    • Slovenia
    • Spain
    • Sweden
    • Switzerland
  • NM View
  • Investments
    • SES RP3

    • Austria
    • Belgium
    • Bulgaria
    • Croatia
    • Cyprus
    • Czech Republic
    • Denmark
    • Estonia
    • Finland
    • France
    • Germany
    • Greece
    • Hungary
    • Ireland
    • Italy
    • Latvia
    • Lithuania
    • Luxembourg
    • Malta
    • MUAC
    • Netherlands
    • Norway
    • Poland
    • Portugal
    • Romania
    • Slovakia
    • Slovenia
    • Spain
    • Sweden
    • Switzerland
  • About
  • Download
  • Data Portal
  • Publications
  1. Investments - Belgium
  • Investments - Belgium
  • PRB monitoring
  • Value of assets
    • By category
    • En route and terminal
    • By type
    • Compared to Union-wide

  • Costs
    • New and existing investments
    • En route
    • Terminal
    • New major investments

  • Expected benefit and impact

  • Public funding

Investments - Belgium

PRB monitoring

▪ skeyes planned a total RP3 asset value for new investments of 103M€₂₀₁₇, of which 35% for new major investments. skeyes planned 4 new major investments for RP3, all of which have started.

▪ skeyes planned RP3 new investments represent 2% of the Union-wide total amounts of the assets for new investments. Compared to the Union-wide median, skeyes planned to invest more in ATM systems (55% vs 47% respectively) and in CNS systems (45% vs 18%).

▪ skeyes underspent -1.9M€₂₀₁₇ (-2.5%) in costs related to investments during RP3 (-1.2M€₂₀₁₇ in en route and -0.7M€₂₀₁₇ in terminal), according to the reporting tables. These amounts shall be reimbursed to the airspace users through a reduction of future unit rate(s), unless the NSA decides after consultation with the users, that the ANSP shall not reimburse a part of the difference according to article 28 of Regulation (EU) 2019/317.

▪ skeyes reported 0.1M€₂₀₁₇ funding from Union assistance programmes in RP3, while SESAR Deployment Manager data indicates payments for 0.4M€₂₀₁₇ during the reference period.

Value of the assets for New Investments included in the Performance Plan Belgium | skeyes

Determined and additional asset value by investment category

Total value of the asset for new investments (M€2017) 102.70 % of total
New major investments (above 5M€ each) 35.47 35%
Included in the performance plan 35.47 35%
Additional 0.00 0%
Other new investments (below 5M€ each) 67.23 65%

Determined asset value: en route and terminal

Total value of the asset for new major investments (M€2017) 35.47 % of total
En route 25.56 72%
Terminal 9.91 28%

Determined asset value by type of investment

Total value of the asset for new major investments (M€2017) 35.47 % of total
ATM systems 19.69 55%
CNS systems 15.78 45%
Infrastructure 0.00 0%
Other 0.00 0%
Unknown 0.00 0%

Asset value for new investments: ANSP compared to Union-wide

Costs related to investments included in the Performance Plan Belgium | skeyes

New and existing investments

Determined costs 2020D 2021D 2022D 2023D 2024D RP3
Total costs of new and existing investments (M€2017) 15.07 13.36 12.98 14.71 18.31 74.43
New major investments 0.02 0.12 0.31 0.90 2.11 3.45
Other new investments 1.22 1.43 1.43 1.19 1.25 6.51
Existing investments 13.84 11.81 11.24 12.62 14.95 64.46
Actual costs 2020A 2021A 2022A 2023A 2024A RP3
Total costs of new and existing investments (M€2017) 15.07 12.95 12.65 15.19 16.66 72.53
New major investments 0.02 0.13 0.29 1.46 2.32 4.21
Other new investments 0.49 0.69 0.97 0.98 7.18 10.32
Existing investments 14.56 12.14 11.39 12.75 7.16 58.00
Difference (A-D) 2020 2021 2022 2023 2024 RP3
Total difference (M€2017) 0.00 (0.40) (0.33) 0.48 (1.64) (1.90)
New major investments 0.00 0.01 (0.02) 0.56 0.21 0.76
% change of actual with respect to determined +0% +8% -8% +63% +10% +73%
Other new investments (0.73) (0.74) (0.45) (0.21) 5.94 3.81
% change of actual with respect to determined -59% -52% -32% -18% +477% +316%
Existing investments 0.73 0.33 0.15 0.13 (7.80) (6.47)
% change of actual with respect to determined +5% +3% +1% +1% -52% -42%


Costs of investments by nature - En route

Determined costs 2020D 2021D 2022D 2023D 2024D RP3
Total costs of new and existing investments (M€2017) 11.59 10.34 10.11 11.31 13.92 57.27
Depreciation 10.03 9.04 8.51 9.05 10.96 47.60
Cost of capital 1.56 1.30 1.60 2.26 2.97 9.67
Cost of leasing 0.00 0.00 0.00 0.00 0.00 0.00
Actual costs 2020A 2021A 2022A 2023A 2024A RP3
Total costs of new and existing investments (M€2017) 11.59 10.00 9.82 11.69 12.98 56.07
Depreciation 10.03 8.77 8.54 9.48 10.25 47.08
Cost of capital 1.56 1.23 1.27 2.21 2.73 8.99
Cost of leasing 0.00 0.00 0.00 0.00 0.00 0.00
Difference (A-D) 2020 2021 2022 2023 2024 RP3
Total difference (M€2017) 0.00 (0.34) (0.29) 0.38 (0.95) (1.19)
Depreciation 0.00 (0.27) 0.03 0.43 (0.71) (0.52)
Cost of capital 0.00 (0.07) (0.32) (0.05) (0.24) (0.68)
Cost of leasing 0.00 0.00 0.00 0.00 0.00 0.00


Costs of investments by nature - Terminal

Determined costs 2020D 2021D 2022D 2023D 2024D RP3
Total costs of new and existing investments (M€2017) 3.48 3.02 2.87 3.40 4.38 17.16
Depreciation 3.01 2.64 2.43 2.69 3.36 14.13
Cost of capital 0.47 0.38 0.45 0.71 1.02 3.02
Cost of leasing 0.00 0.00 0.00 0.00 0.00 0.00
Actual costs 2020A 2021A 2022A 2023A 2024A RP3
Total costs of new and existing investments (M€2017) 3.48 2.96 2.83 3.50 3.69 16.46
Depreciation 3.01 2.59 2.47 2.87 2.89 13.83
Cost of capital 0.47 0.37 0.37 0.63 0.79 2.63
Cost of leasing 0.00 0.00 0.00 0.00 0.00 0.00
Difference (A-D) 2020 2021 2022 2023 2024 RP3
Total difference (M€2017) 0.00 (0.07) (0.04) 0.10 (0.70) (0.70)
Depreciation 0.00 (0.05) 0.04 0.18 (0.47) (0.30)
Cost of capital 0.00 (0.02) (0.08) (0.08) (0.22) (0.40)
Cost of leasing 0.00 0.00 0.00 0.00 0.00 0.00


Costs by new major investments

Determined costs 2020D 2021D 2022D 2023D 2024D RP3
Total costs of new and existing investments (M€2017) 0.02 0.12 0.31 0.90 2.11 3.45
ATM Next Generation 0.00 0.04 0.10 0.28 0.50 0.91
remote radio sites 0.01 0.04 0.10 0.17 0.69 1.01
Wide Area Networking 0.00 0.03 0.09 0.35 0.78 1.26
A-SMGCS 2 systeem EBBR 0.00 0.01 0.02 0.10 0.13 0.27
Actual costs 2020A 2021A 2022A 2023A 2024A RP3
Total costs of new and existing investments (M€2017) 0.02 0.13 0.29 1.46 2.32 4.21
ATM Next Generation 0.00 0.06 0.13 0.45 1.21 1.85
remote radio sites 0.01 0.03 0.05 0.17 0.60 0.87
Wide Area Networking 0.00 0.03 0.05 0.67 0.33 1.07
A-SMGCS 2 systeem EBBR 0.00 0.01 0.06 0.17 0.18 0.43
Difference (A-D) 2020 2021 2022 2023 2024 RP3
Total difference (M€2017) 0.00 0.01 (0.02) 0.56 0.21 0.76
ATM Next Generation 0.00 0.02 0.03 0.17 0.71 0.94
remote radio sites 0.00 (0.01) (0.05) 0.00 (0.09) (0.14)
Wide Area Networking 0.00 (0.01) (0.04) 0.32 (0.45) (0.19)
A-SMGCS 2 systeem EBBR (0.00) 0.00 0.04 0.07 0.04 0.15


Expected benefit and impact per new major investment Belgium | skeyes

New major investments Expected benefit per KPA SAF ENV CAP CEF
Wide Area Networking X X
ATM Next Generation
A-SMGCS 2 systeem EBBR
remote radio sites X X
New major investments Expected impact Network Local Non-performance
Wide Area Networking X X
ATM Next Generation
A-SMGCS 2 systeem EBBR
remote radio sites X X


New major investments SES mandated Partnership
ATM systems
ATM system CP/MP
Wide Area Networking
ATM Next Generation X X X X
A-SMGCS 2 systeem EBBR X
remote radio sites X


Public funding granted for total CAPEX (CEF/TEN-T)

Actual funding declaration vs payments

Funding declared (M€2017) 2020 2021 2022 2023 2024 RP3
Total included in the funding declaration (reporting tables) 0.13 0.00 0.00 0.00 0.00 0.13
SDM Payment 0.00 0.11 0.06 0.00 0.25 0.42
Difference between total funding declared vs received 0.13 (0.11) (0.06) 0.00 (0.25) (0.29)


 