• Home
  • SES view
  • State view
    • Austria
    • Belgium
    • Bulgaria
    • Croatia
    • Cyprus
    • Czech Republic
    • Denmark
    • Estonia
    • Finland
    • France
    • Germany
    • Greece
    • Hungary
    • Ireland
    • Italy
    • Latvia
    • Lithuania
    • Luxembourg
    • Malta
    • MUAC
    • Netherlands
    • Norway
    • Poland
    • Portugal
    • Romania
    • Slovakia
    • Slovenia
    • Spain
    • Sweden
    • Switzerland
  • NM View
  • Investments
    • SES RP3

    • Austria
    • Belgium
    • Bulgaria
    • Croatia
    • Cyprus
    • Czech Republic
    • Denmark
    • Estonia
    • Finland
    • France
    • Germany
    • Greece
    • Hungary
    • Ireland
    • Italy
    • Latvia
    • Lithuania
    • Luxembourg
    • Malta
    • MUAC
    • Netherlands
    • Norway
    • Poland
    • Portugal
    • Romania
    • Slovakia
    • Slovenia
    • Spain
    • Sweden
    • Switzerland
  • About
  • Download
  • Data Portal
  • Publications
  1. Investments - Ireland
  • Investments - Ireland
  • PRB monitoring
  • Value of assets
    • By category
    • En route and terminal
    • By type
    • Compared to Union-wide

  • Costs
    • New and existing investments
    • En route
    • Terminal
    • New major investments

  • Expected benefit and impact

  • Public funding

Investments - Ireland

PRB monitoring

▪ AirNav Ireland planned a total RP3 asset value for new investments of 141M€₂₀₁₇, of which 72% for new major investments. AirNav Ireland planned 10 new major investments for RP3, of which two have not started.

▪ AirNav Ireland planned RP3 new investments represent 3% of the Union-wide total amounts of the assets for new investments. AirNav Ireland planned to invest more in infrastructure compared to the Union-wide median (58% vs 27% respectively), and less for CNS systems (11% vs 18%).

▪ AirNav Ireland underspent -15M€₂₀₁₇ (-18%) in costs related to investments during RP3 (-8.4M€₂₀₁₇ in en route and -6.9M€₂₀₁₇ in terminal), according to the reporting tables. However, in the monitoring reports, AirNav Ireland reported an underspending of -17M€₂₀₁₇ (-19%). No explanation for the differences has been provided. These amounts shall be reimbursed to the airspace users through a reduction of future unit rate(s), unless the NSA decides after consultation with the users, that the ANSP shall not reimburse a part of the difference according to article 28 of Regulation (EU) 2019/317.

▪ AirNav Ireland reported no funding from Union assistance programmes in RP3, while SESAR Deployment Manager data indicates payments for 3.9M€₂₀₁₇ during the reference period.

Value of the assets for New Investments included in the Performance Plan Ireland | AirNav Ireland

Determined and additional asset value by investment category

Total value of the asset for new investments (M€2017) 140.90 % of total
New major investments (above 5M€ each) 101.05 72%
Included in the performance plan 101.05 72%
Additional 0.00 0%
Other new investments (below 5M€ each) 39.85 28%

Determined asset value: en route and terminal

Total value of the asset for new major investments (M€2017) 101.05 % of total
En route 35.83 35%
Terminal 65.22 65%

Determined asset value by type of investment

Total value of the asset for new major investments (M€2017) 101.05 % of total
ATM systems 31.47 31%
CNS systems 11.20 11%
Infrastructure 58.38 58%
Other 0.00 0%
Unknown 0.00 0%

Asset value for new investments: ANSP compared to Union-wide

Costs related to investments included in the Performance Plan Ireland | AirNav Ireland

New and existing investments

Determined costs 2020D 2021D 2022D 2023D 2024D RP3
Total costs of new and existing investments (M€2017) 10.36 15.32 19.68 21.50 20.78 87.63
New major investments 0.13 4.33 7.94 10.46 11.18 34.04
Other new investments 0.18 0.95 3.64 5.35 6.45 16.57
Existing investments 10.04 10.05 8.09 5.70 3.14 37.03
Actual costs 2020A 2021A 2022A 2023A 2024A RP3
Total costs of new and existing investments (M€2017) 10.36 13.30 16.13 15.96 15.22 70.97
New major investments 0.13 2.69 7.02 8.17 8.83 26.84
Other new investments 0.18 0.56 1.65 2.44 3.46 8.28
Existing investments 10.04 10.05 7.47 5.36 2.94 35.85
Difference (A-D) 2020 2021 2022 2023 2024 RP3
Total difference (M€2017) 0.00 (2.02) (3.54) (5.53) (5.56) (16.66)
New major investments 0.00 (1.64) (0.92) (2.29) (2.35) (7.20)
% change of actual with respect to determined 0% -38% -12% -22% -21% -92%
Other new investments 0.00 (0.39) (2.00) (2.91) (3.00) (8.29)
% change of actual with respect to determined 0% -41% -55% -54% -46% -197%
Existing investments 0.00 0.00 (0.63) (0.34) (0.21) (1.18)
% change of actual with respect to determined 0% +0% -8% -6% -7% -20%


Costs of investments by nature - En route

Determined costs 2020D 2021D 2022D 2023D 2024D RP3
Total costs of new and existing investments (M€2017) 7.48 10.06 11.23 12.01 11.11 51.90
Depreciation 6.34 7.60 8.35 8.67 7.86 38.82
Cost of capital 1.14 2.46 2.88 3.34 3.26 13.08
Cost of leasing 0.00 0.00 0.00 0.00 0.00 0.00
Actual costs 2020A 2021A 2022A 2023A 2024A RP3
Total costs of new and existing investments (M€2017) 8.45 9.62 8.94 8.52 7.92 43.45
Depreciation 6.61 7.27 6.66 6.33 5.67 32.53
Cost of capital 1.85 2.35 2.27 2.19 2.25 10.91
Cost of leasing 0.00 0.00 0.00 0.00 0.00 0.00
Difference (A-D) 2020 2021 2022 2023 2024 RP3
Total difference (M€2017) 0.97 (0.44) (2.29) (3.49) (3.19) (8.45)
Depreciation 0.26 (0.33) (1.69) (2.35) (2.19) (6.29)
Cost of capital 0.70 (0.11) (0.61) (1.15) (1.00) (2.17)
Cost of leasing 0.00 0.00 0.00 0.00 0.00 0.00


Costs of investments by nature - Terminal

Determined costs 2020D 2021D 2022D 2023D 2024D RP3
Total costs of new and existing investments (M€2017) 2.87 5.26 8.45 9.49 9.67 35.73
Depreciation 2.44 3.45 4.93 5.51 5.60 21.93
Cost of capital 0.43 1.81 3.52 3.98 4.06 13.80
Cost of leasing 0.00 0.00 0.00 0.00 0.00 0.00
Actual costs 2020A 2021A 2022A 2023A 2024A RP3
Total costs of new and existing investments (M€2017) 3.21 3.68 7.20 7.45 7.29 28.83
Depreciation 2.48 2.69 3.90 4.04 3.93 17.03
Cost of capital 0.73 0.99 3.30 3.41 3.37 11.80
Cost of leasing 0.00 0.00 0.00 0.00 0.00 0.00
Difference (A-D) 2020 2021 2022 2023 2024 RP3
Total difference (M€2017) 0.34 (1.58) (1.25) (2.04) (2.37) (6.91)
Depreciation 0.04 (0.77) (1.03) (1.47) (1.67) (4.90)
Cost of capital 0.30 (0.82) (0.22) (0.57) (0.70) (2.00)
Cost of leasing 0.00 0.00 0.00 0.00 0.00 0.00


Costs by new major investments

Determined costs 2020D 2021D 2022D 2023D 2024D RP3
Total costs of new and existing investments (M€2017) 0.13 4.33 7.94 10.46 11.18 34.04
COOPANS Builds 3.6 to 3.8 budget 0.00 0.26 0.81 0.99 0.95 3.01
New Dublin Radar 2 Replacement 0.00 0.00 0.06 0.26 0.25 0.57
NAVAIDS replacement program 0.00 0.01 0.14 0.32 0.56 1.04
Dublin Tower - Building 0.00 1.47 3.05 3.00 2.98 10.50
Dublin Tower - Equipment 0.00 0.68 1.78 2.36 2.28 7.11
COOPANS 2019 Roadmap Builds 0.00 0.00 0.00 0.02 0.26 0.28
New En Route Contingency Centre at Ballygireen 0.13 1.89 1.86 1.81 1.72 7.41
Emergency Air Situation Display System (EASDS) Replacement 0.00 0.00 0.16 0.95 1.02 2.14
Climate Action Plan (Sustainability Management Plan) 0.00 0.02 0.08 0.27 0.50 0.86
Plant upgrade works 0.00 0.00 0.00 0.46 0.65 1.11
Actual costs 2020A 2021A 2022A 2023A 2024A RP3
Total costs of new and existing investments (M€2017) 0.13 2.69 7.02 8.17 8.83 26.84
COOPANS Builds 3.6 to 3.8 budget 0.00 0.00 0.62 1.15 1.64 3.41
New Dublin Radar 2 Replacement 0.00 0.00 0.00 0.00 0.00 0.00
NAVAIDS replacement program 0.00 0.00 0.03 0.08 0.17 0.29
Dublin Tower - Building 0.00 0.52 3.15 3.20 3.15 10.02
Dublin Tower - Equipment 0.00 0.17 1.36 1.80 1.78 5.10
COOPANS 2019 Roadmap Builds 0.00 0.00 0.00 0.00 0.14 0.14
New En Route Contingency Centre at Ballygireen 0.13 2.00 1.86 1.94 1.88 7.81
Emergency Air Situation Display System (EASDS) Replacement 0.00 0.00 0.00 0.00 0.00 0.00
Climate Action Plan (Sustainability Management Plan) 0.00 0.00 0.00 0.00 0.06 0.06
Plant upgrade works 0.00 0.00 0.00 0.00 0.01 0.01
Difference (A-D) 2020 2021 2022 2023 2024 RP3
Total difference (M€2017) (0.00) (1.64) (0.92) (2.29) (2.35) (7.20)
COOPANS Builds 3.6 to 3.8 budget 0.00 (0.26) (0.19) 0.16 0.69 0.40
New Dublin Radar 2 Replacement 0.00 0.00 (0.06) (0.26) (0.25) (0.57)
NAVAIDS replacement program 0.00 (0.01) (0.11) (0.24) (0.39) (0.76)
Dublin Tower - Building 0.00 (0.95) 0.10 0.20 0.17 (0.48)
Dublin Tower - Equipment 0.00 (0.51) (0.42) (0.57) (0.50) (2.00)
COOPANS 2019 Roadmap Builds 0.00 0.00 0.00 (0.02) (0.12) (0.14)
New En Route Contingency Centre at Ballygireen (0.00) 0.11 (0.00) 0.13 0.16 0.39
Emergency Air Situation Display System (EASDS) Replacement 0.00 0.00 (0.16) (0.95) (1.02) (2.14)
Climate Action Plan (Sustainability Management Plan) 0.00 (0.02) (0.08) (0.27) (0.44) (0.80)
Plant upgrade works 0.00 0.00 (0.00) (0.46) (0.64) (1.11)


Expected benefit and impact per new major investment Ireland | AirNav Ireland

New major investments Expected benefit per KPA SAF ENV CAP CEF
Dublin Tower - Building X X
New En Route Contingency Centre at Ballygireen X X X
Dublin Tower - Equipment X X
COOPANS Builds 3.6 to 3.8 budget X X X X
NAVAIDS replacement program X X X
Plant upgrade works X X
Climate Action Plan (Sustainability Management Plan) X
New Dublin Radar 2 Replacement X X X X
COOPANS 2019 Roadmap Builds X X X X
Emergency Air Situation Display System (EASDS) Replacement X
New major investments Expected impact Network Local Non-performance
Dublin Tower - Building X X
New En Route Contingency Centre at Ballygireen X X
Dublin Tower - Equipment X X
COOPANS Builds 3.6 to 3.8 budget X X
NAVAIDS replacement program X X
Plant upgrade works X X
Climate Action Plan (Sustainability Management Plan) X
New Dublin Radar 2 Replacement X X
COOPANS 2019 Roadmap Builds X X
Emergency Air Situation Display System (EASDS) Replacement X X


New major investments SES mandated Partnership
ATM systems
ATM system CP/MP
Dublin Tower - Building X
New En Route Contingency Centre at Ballygireen X X
Dublin Tower - Equipment X X X
COOPANS Builds 3.6 to 3.8 budget X X X X
NAVAIDS replacement program X X X
Plant upgrade works
Climate Action Plan (Sustainability Management Plan) X
New Dublin Radar 2 Replacement X X
COOPANS 2019 Roadmap Builds X X X X
Emergency Air Situation Display System (EASDS) Replacement X X X


Public funding granted for total CAPEX (CEF/TEN-T)

Actual funding declaration vs payments

Funding declared (M€2017) 2020 2021 2022 2023 2024 RP3
Total included in the funding declaration (reporting tables) 0.00 0.00 0.00 0.00 0.00 0.00
SDM Payment -0.53 1.42 0.79 0.63 1.59 3.90
Difference between total funding declared vs received 0.53 (1.42) (0.79) (0.63) (1.59) (3.90)


 