Investments - Norway
PRB monitoring
▪ Avinor ANS planned a total RP3 asset value for new investments of 81M€₂₀₁₇, of which 52% for new major investments. Avinor ANS planned four new major investments for RP3.
▪ Avinor ANS planned RP3 new investments represent 2% of the Union-wide total amounts of the assets for new investments. Avinor ANS planned to invest more in ATM systems compared to the Union-wide median 63% vs 47% respectively).
▪ Avinor ANS underspent -1.7M€₂₀₁₇ (-1.2%) in costs related to investments during RP3 (-1.2M€₂₀₁₇ in en route and -0.5M€₂₀₁₇ in terminal), according to the reporting tables. However, in the monitoring reports, Avinor ANS reported an underspending of -0.6M€₂₀₁₇ (-0.5%). No explanation for the differences has been provided. These amounts shall be reimbursed to the airspace users through a reduction of future unit rate(s), unless the NSA decides after consultation with the users, that the ANSP shall not reimburse a part of the difference according to article 28 of Regulation (EU) 2019/317.
▪ Avinor ANS reported no funding from Union assistance programmes in RP3, while SESAR Deployment Manager data indicates payments for 1.1M€₂₀₁₇ during the reference period.
Expected benefit and impact per new major investment Norway | Avinor Flysikring AS (Avinor ANS)
| New major investments |
Expected benefit per KPA |
SAF |
ENV |
CAP |
CEF |
| SKYCOM |
|
|
|
|
|
| Terminal area radar OSL |
|
|
|
|
|
| New ATM system OSL, NeTSO |
|
X |
|
X |
X |
| Future TWR system |
|
|
|
|
|
| New major investments |
Expected impact |
Network |
Local |
Non-performance |
| SKYCOM |
|
X |
X |
|
| Terminal area radar OSL |
|
X |
X |
|
| New ATM system OSL, NeTSO |
|
|
|
|
| Future TWR system |
|
X |
X |
|
| New major investments |
SES mandated |
Partnership |
ATM systems
|
| ATM system |
CP/MP |
| SKYCOM |
|
|
|
X |
| Terminal area radar OSL |
|
|
|
X |
| New ATM system OSL, NeTSO |
X |
|
X |
|
| Future TWR system |
|
|
|
X |
Public funding granted for total CAPEX (CEF/TEN-T)
Actual funding declaration vs payments
| Funding declared (M€2017) |
2020 |
2021 |
2022 |
2023 |
2024 |
RP3 |
| Total included in the funding declaration (reporting tables) |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
| SDM Payment |
0.00 |
0.00 |
1.07 |
0.00 |
0.00 |
1.07 |
| Difference between total funding declared vs received |
0.00 |
0.00 |
(1.07) |
0.00 |
0.00 |
(1.07) |