AUC vs. DUC
In 2024, the terminal AUC was +22.4% (or +29.09 €2017) higher than the planned DUC. This results from the combination of significantly lower than planned TNSUs (-21.3%) and lower than planned terminal costs in real terms (-3.7%, or -0.2 M€2017). It should be noted that the actual inflation index in 2024 was +12.8 p.p. higher than planned.
Terminal service units
The difference between actual and planned TNSUs (-21.3%) falls outside the ±10% threshold foreseen in the traffic risk sharing mechanism. The resulting loss of terminal revenues is therefore shared between the ANSP and the airspace users (see the main ANSP loss in Box 11).
Terminal costs by entity
Actual real terminal costs are -3.7% (-0.2 M€2017) lower than planned. This is the result of lower costs for the main ANSP, LGS (-4.2%, or -0.3 M€2017) and the MET service provider (-26.6%, or -0.04 M€2017) and higher costs for the NSA (+23.7%, or +0.1 M€2017).
Terminal costs for the main ANSP at charging zone level
Lower than planned terminal costs in real terms for LGS in 2024 (-4.2%, or -0.3 M€2017) are affected by the impact of inflation index (+12.8 p.p.) since, in nominal terms, the costs were slightly above planned (+3.4%). The variation in real terms results from:
- Higher staff costs (+3.0%) due to “higher than planned inflation, collective agreement changes, and higher sick-leaves”,
- Significantly higher other operating costs (+20.0%) explained by “unplanned expert opinion for Riga Enhanced ATM Infrastructure Development (REACT) project as required by auditors”,
- Significantly lower depreciation (-15.1%) reflecting delays in above-mentioned REACT project,
- Significantly lower cost of capital (-13.4%) resulting from lower than planned asset-base.
- A deduction of costs for VFR exempted flights (-0.1 M€2017) while none were foreseen in the PP.
RP3 summary
When considering the whole of RP3 (2020-2024) for Latvia terminal charging zone, actual TNSUs are -13.8% lower than planned, while actual costs in real terms are -3.0% lower than the determined costs (some -0.9 M€2017). As a result, the weighted average actual unit cost over RP3 (195.28 €2017) is +12.6% higher than planned in the PP (173.40 €2017).