Cost-efficiency - Belgium
PRB monitoring
▪ The en route 2024 actual unit cost of Belgium-Luxembourg was 87.09€2017, +8.5% higher than the determined unit cost (80.26€2017). The terminal 2024 actual unit cost of Belgium was 232.99€2017, +5.3% higher than the determined unit cost (221.23€2017).
▪ The en route 2024 actual service units (2.5M) were -1.8% lower than the determined service units (2.6M).
▪ The en route 2024 actual total costs were +13M€2017 (+6.6%) higher than determined. The gap was mainly due to the negative exceptional item which was included in the determined costs to achieve the RP3 cost-efficiency targets, but is not included in the actual costs. This was partially offset by lower staff costs than planned (-8.6M€2017, or -8.4%) for skeyes, which the NSA attributed to difficulties in recruitment.
▪ Skeyes costs of investments were 18M€2017 in 2024 for both en route and terminal charging zones, -9.8% less than determined (20M€2017). According to the NSA, this difference is due to projects delays and a lower fixed asset base.
▪ The en route actual unit cost incurred by users in 2024 was 97.80€ (-0.7% below the 2024 DUC). The terminal actual unit cost incurred by users was 186.67€ (-31% below the 2024 DUC) for Belgium and 226.12€ (-14% below the 2024 DUC) for Luxembourg. The differences between the AUCU and the DUC for the terminal charging zones of Belgium and Luxembourg are mainly affected by the adjustment of other revenues.
En route charging zone
Unit cost (KPI#1)
| Actual and determined data | ||||
| Total costs - nominal (M€) | 2020-2021 | 2022 | 2023 | 2024 |
|---|---|---|---|---|
| Actual costs | 432 | 240 | 255 | 269 |
| Determined costs | 442 | 250 | 262 | 252 |
| Difference costs | -10 | -10 | -7 | 17 |
| Inflation assumptions | 2020-2021 | 2022 | 2023 | 2024 |
|---|---|---|---|---|
| Determined inflation rate | NA | 7.8% | 4.7% | 2.1% |
| Determined inflation index | NA | 115.6 | 123.9 | 126.5 |
| Actual inflation rate | NA | 10.3% | 2.3% | 4.3% |
| Actual inflation index | NA | 118.3 | 121 | 126.2 |
| Difference inflation index (p.p.) | NA | +2.7 | -2.8 | -0.3 |
Actual unit cost incurred by the users (AUCU) (PI#1)
| AUCU components (€/SU) – 2024 | |
| Components of the AUCU in 2024 | €/SU |
|---|---|
| DUC | 98.47 |
| Inflation adjustment | -0.18 |
| Cost exempt from cost-sharing | -0.21 |
| Traffic risk sharing adjustment | 0.00 |
| Traffic adj. (costs not TRS) | 0.15 |
| Finantial incentives | 0.16 |
| Modulation of charges | 0.00 |
| Cross-financing | 0.00 |
| Other revenues | -0.58 |
| Application of lower unit rate | 0.00 |
| Total adjustments | -0.67 |
| AUCU | 97.80 |
| AUCU vs. DUC | -0.7% |
| Cost exempt from cost sharing by item - 2024 | €'000 | €/SU |
|---|---|---|
| New and existing investments | -1,294.4 | -0.51 |
| Competent authorities and qualified entities costs | 16.0 | 0.01 |
| Eurocontrol costs | -57.8 | -0.02 |
| Pension costs | 805.2 | 0.32 |
| Interest on loans | 0.0 | 0.00 |
| Changes in law | 0.0 | 0.00 |
| Total cost exempt from cost risk sharing | -531.0 | -0.21 |