Cost-efficiency - Sweden
PRB monitoring
▪ The en route 2024 actual unit cost of Sweden was 17.15€2017, -72% lower than the determined unit cost (61.00€2017). The terminal 2024 actual unit cost was 19.90€2017, -85% lower than the determined unit cost (131.71€2017).
▪ The en route 2024 actual service units of Sweden (2.9M) were -15% lower than the determined service units (3.4M), mainly due to shifted traffic flows caused by Russia’s war of aggression against Ukraine.
▪ The en route 2024 actual total costs were -156M€2017 (-76%) lower than the determined. This difference is driven by negative exceptional costs for LFV. Although no exceptional costs had been planned, the actual exceptional costs were -185M€2017, which was due to a one-time effect on pension costs resulting from increased interest rates that reduced the pension debt. When excluding this item, the en route 2024 actual total costs for Sweden are +28M€2017 (+14%) higher than planned.
▪ LFV spent 20M€2017 in 2024 related to costs of investments for both en route and terminal charging zones, +11% higher than determined (18M€2017). The difference is driven by higher depreciation costs under the RTS-Swedavia program, resulting from a combination of higher total investment and depreciation period shorter than originally planned.
▪ The en route actual unit cost incurred by users in 2024 was 10.25€ (-82% lower than the 2024 DUC), while the terminal actual unit cost incurred by users in 2024 was 18.30€ (-86% lower than the 2024 DUC). The difference between the AUCU and the DUC is mostly resulting from the cost risk sharing adjustment for both en route and terminal charging zones.
▪ Sweden should take additional measures to manage the cost-risk associated with pensions for RP4 in view of wide fluctuations in actual pension costs observed during RP3.
En route charging zone
Unit cost (KPI#1)
| Actual and determined data | ||||
| Total costs - nominal (M€) | 2020-2021 | 2022 | 2023 | 2024 |
|---|---|---|---|---|
| Actual costs | 496 | 246 | 292 | 48 |
| Determined costs | 502 | 240 | 245 | 232 |
| Difference costs | -6 | 7 | 48 | -184 |
| Inflation assumptions | 2020-2021 | 2022 | 2023 | 2024 |
|---|---|---|---|---|
| Determined inflation rate | NA | 4.8% | 2.2% | 1.7% |
| Determined inflation index | NA | 112.4 | 114.9 | 116.9 |
| Actual inflation rate | NA | 8.1% | 5.9% | 2.0% |
| Actual inflation index | NA | 116 | 122.8 | 125.3 |
| Difference inflation index (p.p.) | NA | +3.5 | +7.9 | +8.4 |
Actual unit cost incurred by the users (AUCU) (PI#1)
| AUCU components (€/SU) – 2024 | |
| Components of the AUCU in 2024 | €/SU |
|---|---|
| DUC | 58.08 |
| Inflation adjustment | 3.88 |
| Cost exempt from cost-sharing | -58.47 |
| Traffic risk sharing adjustment | 5.93 |
| Traffic adj. (costs not TRS) | 1.47 |
| Finantial incentives | 0.49 |
| Modulation of charges | 0.00 |
| Cross-financing | 0.00 |
| Other revenues | -1.14 |
| Application of lower unit rate | 0.00 |
| Total adjustments | -47.84 |
| AUCU | 10.25 |
| AUCU vs. DUC | -82.4% |
| Cost exempt from cost sharing by item - 2024 | €'000 | €/SU |
|---|---|---|
| New and existing investments | 735.2 | 0.26 |
| Competent authorities and qualified entities costs | 1,833.9 | 0.64 |
| Eurocontrol costs | 1,022.5 | 0.36 |
| Pension costs | -171,832.3 | -59.78 |
| Interest on loans | 172.9 | 0.06 |
| Changes in law | 0.0 | 0.00 |
| Total cost exempt from cost risk sharing | -168,067.8 | -58.47 |