| Total value of the asset for new investments (M€2022) | 19.30 | % of total |
|---|---|---|
| New major investments (above 5M€ each) | 4.59 | 24% |
| Included in the performance plan | 4.59 | 24% |
| Additional | 0.00 | 0% |
| Other new investments (below 5M€ each) | 14.71 | 76% |
Investments - Latvia
PRB monitoring
LGS planned a total asset value for new investments in RP4 of 19.3M€2022, of which 23.8% relates to new major investments. LGS planned 1 new major investment for RP4, which has started.
In 2025, LGS overspent +0.01M€2022 (+47.3%) in costs related to new major investments. This is due to the commissioning of core projects.
According to the reporting tables, LGS underspent -0.4M€2022 (-7.3%) in costs related to investments in 2025. These amounts must be reimbursed to the airspace users through a reduction of future unit rate(s), unless the NSA decides after consultation with the users, that the ANSP must not reimburse a part of the difference according to article 28 of Regulation (EU) 2019/317.
LGS reported 0.1M€2022 in funding from Union assistance programmes in 2025.
Value of the assets for New Investments included in the Performance Plan Latvia | LGS and comparison with Union-wide
Determined and additional asset value by investment category
| LGS asset value of new investments compared to Union-wide (%) | 0.4% |
Determined asset value: en route and terminal
| Total value of the asset for new major investments (M€2022)1 | 4.59 | % of total |
|---|---|---|
| En route | 4.59 | 100% |
| Terminal | 0.00 | 0% |
| 1 For investments where the allocation has not been clearly provided, an allocation has been assumed based on available information. | ||
Determined asset value by type of investment
| New ATM system | 4.59 |
| Overhaul of existing ATM system | 4.59 |
| Other ATM | 0.00 |
| CNS | 0.00 |
| Infrastructure | 0.00 |
| Ancillary | 0.00 |
| Other | 0.00 |
| Unknown | 0.00 |
| 1 When summing the assets for new major investments by investment type, the total may differ from the overall asset value for new major investments, as some investments have been categorised under multiple investment types. | |
Expected benefit and impact per new major investment Latvia | LGS
| New major investments | SES mandated | Partnership |
|---|---|---|
| New ATC system | X |