| Total value of the asset for new investments (M€2022) | 193.97 | % of total |
|---|---|---|
| New major investments (above 5M€ each) | 97.44 | 50% |
| Included in the performance plan | 97.44 | 50% |
| Additional | 0.00 | 0% |
| Other new investments (below 5M€ each) | 96.53 | 50% |
Investments - Bulgaria
PRB monitoring
BULATSA planned a total asset value for new investments in RP4 of 194.0M€2022, of which 50.2% relates to new major investments. BULATSA planned 6 new major investments for RP4, of which 4 have started and 2 have not yet started.
In 2025, BULATSA underspent -0.3M€2022 (-19.0%) in costs related to new major investments. This is mainly attributable to the new ATM, simulator and contingency system.
According to the reporting tables, BULATSA overspent +0.4M€2022 (+1.8%) in costs related to investments in 2025.
BULATSA reported 0.1M€2022 in funding from Union assistance programmes in 2025.
Value of the assets for New Investments included in the Performance Plan Bulgaria | BULATSA and comparison with Union-wide
Determined and additional asset value by investment category
| BULATSA asset value of new investments compared to Union-wide (%) | 4.0% |
Determined asset value: en route and terminal
| Total value of the asset for new major investments (M€2022)1 | 97.44 | % of total |
|---|---|---|
| En route | 97.44 | 100% |
| Terminal | 0.00 | 0% |
| 1 For investments where the allocation has not been clearly provided, an allocation has been assumed based on available information. | ||
Determined asset value by type of investment
| New ATM system | 0.00 |
| Overhaul of existing ATM system | 0.00 |
| Other ATM | 0.00 |
| CNS | 0.00 |
| Infrastructure | 59.04 |
| Ancillary | 59.04 |
| Other | 0.00 |
| Unknown | 38.41 |
| 1 When summing the assets for new major investments by investment type, the total may differ from the overall asset value for new major investments, as some investments have been categorised under multiple investment types. | |
Expected benefit and impact per new major investment Bulgaria | BULATSA
| New major investments | SES mandated | Partnership |
|---|---|---|
| Building of Contingency and Data Center and Equipment | ||
| Distributed virtualization infrastructure | ||
| Modernisation of the Operatiоns Room of Sofia Air Traffic Control centre (ATCC) | ||
| Modernization of DVOR/DME | ||
| Modernization of Voice Communication Systems (VCS) in Air Traffic Control Centers in Sofia, Varna and Burgas | ||
| New V4 of the SATCAS ATM System, Simulator and Contingency ATM System | X |