Cost-efficiency - Hungary
PRB monitoring
The en route 2025 actual unit cost of Hungary was 28.24€2022, -8.4% lower than the determined unit cost (30.81€2022). The terminal 2025 actual unit cost was 256.88€2022, -9.4% lower than the determined unit cost (283.49€2022).
The en route 2025 actual service units (4.4M) were +9.5% higher than the determined service units (4.0M).
The en route 2025 actual total costs were slightly higher than determined (+0.4M€2022, or+0.3%). This is entirely driven by higher staff costs, as all other cost categories registered lower costs than planned. Staff costs for HungaroControl were +4.9M€2022 higher than planned (+9.2%). The NSA explained this increase by higher-than-planned personnel expenditure related to measures for increasing capacity and pay rises reflecting inflation.
A deviation from the criteria to achieve capacity targets was considered justified for Hungary. Actual costs for the measures necessary to achieve those targets were lower than determined (-0.8M€2022, or -11.7%), mainly due to lower other operating costs (-0.7M€2022, or -18.9%) than planned.
HungaroControl spent 33.1M€2022 in 2025 related to costs of investments for both en route and terminal charging zones, -11.9% less than determined (37.5M€2022). The NSA explained that this reduction is mainly due to postponed investments and delayed developments.
The en route actual unit cost incurred by users in 2025 was 32.66€ (-8.4% below the 2025 DUC), while the terminal actual unit cost incurred by users was 277.22€ (-13.7% below the 2025 DUC). The difference between the AUCU and the DUC for both terminal and en route charging zones is mainly driven by the traffic risk sharing adjustment.
En route charging zone
Unit cost (KPI#1)
| Actual and determined data | |||||
| Total costs - nominal (M€) | 2025 | 2026 | 2027 | 2028 | 2029 |
|---|---|---|---|---|---|
| Determined costs | 144.8 | 155.5 | 165.2 | 173.0 | 189.1 |
| Actual costs | 147.1 | NA | NA | NA | NA |
| Difference costs | 2.3 | NA | NA | NA | NA |
| Inflation assumptions | 2025 | 2026 | 2027 | 2028 | 2029 |
|---|---|---|---|---|---|
| Determined inflation rate | 3.5% | 2.9% | 3.0% | 3.0% | 3.0% |
| Determined inflation index* | 125.7 | 129.3 | 133.2 | 137.2 | 141.3 |
| Actual inflation rate | 4.4% | NA | NA | NA | NA |
| Actual inflation index* | 126.7 | NA | NA | NA | NA |
| Difference inflation index (p.p.) | +1 | NA | NA | NA | NA |
| *100 = 2022 | |||||
Actual unit cost incurred by the users (AUCU) (PI#1)
| AUCU components (€/SU) – 2025 | |
| €/SU | |
|---|---|
| DUC | 35.64 |
| Inflation adjustment | 0.19 |
| Cost exempt from cost sharing | -0.71 |
| Traffic risk sharing adjustment | -1.53 |
| Traffic adjustment (costs not TRS) | -0.31 |
| Financial incentives | 0.00 |
| Modulation of charges | 0.00 |
| Cross-financing | 0.00 |
| Other revenues | -0.62 |
| Application of lower unit rate | 0.00 |
| Total adjustments | -2.98 |
| AUCU | 32.66 |
| AUCU vs. DUC | -8.4% |
| Cost exempt from cost sharing by item - 2025 | €'000 | €/SU |
|---|---|---|
| New and existing investments | -3,580.6 | -0.82 |
| Competent authorities and qualified entities costs | -263.2 | -0.06 |
| Eurocontrol costs | 732.4 | 0.17 |
| Pension costs | 0.0 | 0.00 |
| Interest on loans | 0.0 | 0.00 |
| Changes in law | 0.0 | 0.00 |
| Total cost exempt from cost risk sharing | -3,111.4 | -0.71 |