AUC vs. DUC
In 2025, the terminal AUC was +3.7% (or +8.95 €2022) higher than the planned DUC. This results from the combination of higher than planned terminal costs in real terms (+2.8%, or +1.4 M€2022) and slightly lower than planned TNSUs (-0.9%).
Terminal service units
The difference between actual and planned TNSUs (-0.9%) falls inside the ±2% dead-band. Hence, the loss of terminal revenues is borne by the ANSPs.
Terminal costs by entity
Actual real terminal costs are +2.8% (+1.4 M€2022) higher than planned. This is the result of higher costs for the main ANSP, Austro Control (+3.4%, or +1.6 M€2022) and the NSA (+19.1%, or +0.03 M€2022) and lower costs for the MET service provider (-7.8%, or -0.3 M€2022).
Terminal costs for the main ANSP (Austro Control) at charging zone level
Based on the additional information to the terminal reporting tables, the higher than planned terminal costs in real terms for Austro Control in 2025 (+3.4%, or +1.6 M€2022) result from:
Significantly higher than planned staff costs (+5.7%), mainly due to higher than foreseen inflation and its effects on pension costs.
Lower than planned other operating costs (-5.0%).
Slightly lower than planned depreciation (-0.9%).
Slightly higher than planned cost of capital (+1.8%).
Slightly lower than planned exceptional costs (-0.9%), due to the effect of higher than planned inflation index (+1.1 p.p.) since in nominal terms the actual costs were equal to those planned.
Assessment of the actual performance in the charging zone reported by the NSA
The NSA of Austria provides the following overall assessment of the actual performance in 2025 at charging zone level:
“Higher costs together with a higher inflation and less traffic than determined led to higher real en route unit costs.”
[It should be noted that the extract from the NSA 2025 monitoring report cited above refers to “en-route” whereas it is reported under “terminal ANS” section of the report.]
Explanation of the differences between actual and determined costs at charging zone level reported by the NSA
The NSA provides the following explanation for the differences between actual and determined costs in the charging zone:
“Actual staff costs have been influenced by the higher than determined pension costs which are not within the ANSPs direct influence.”
Recommendations formulated by the NSA to the ANSP (Austro Control) to rectify the situation and actions taken by the ANSP
No information was provided in the NSA 2025 Monitoring Report.